Overview
PlanRadar can detect and highlight scheduling conflicts that need to be fixed. It will indicate unaligned parent phases and dependencies that cannot be fulfilled when using manual scheduling mode.
Read the general introduction to Schedules and Create a Schedule to get a basic understanding about this feature.
Access & permissions
Schedules is available to Pro and Enterprise accounts. Read more in Pricing and Subscription.
To create or edit schedules (only in the Webapp) you need an in-house user with a role permission to manage schedules. Read more in Permissions.
How to access Schedule
- Click Schedule
Unaligned Parent Phase
This conflict occurs if a manually scheduled phase has any sub-elements that lie outside, i.e. start earlier or end earlier. It will also occur if all its sub-elements start later or end earlier.
In this example the parent phase 'Apply for Permits' gets highlighted in red, because its end date is earlier than the end date of its sub-phase 'Permit A'.
To resolve the conflict:
- Click on the conflict highlighted in red and choose:
- Click Adjust phase to keep the phase in manual scheduling mode and just update the start/end dates to fitt the sub-elements.
- OR Click Switch to auto to change to automatic scheduling mode which will automatically fix the issue as a consequence.
To resolve the conflict manually, edit the parent phase and align the start and end dates accordingly, as described in Create, Edit or Delete a Phase > Edit a Phase.